The Town Land Use Zoning Ordinance controls allowed structures, dimensional standards, shoreland areas, parking, signs, and development review. Existing bedrooms, accessory spaces, decks, septic capacity, and parking require records that match the property as built. Code Enforcement and Planning handles zoning and building questions at 207-276-5731. A purchase contract can make satisfactory municipal record review a condition of closing.
The Land Use Zoning Ordinance, amended May 5, 2026, defines a residential dwelling unit as rooms for one family at a time with cooking, toilet and sleeping facilities, including seasonal or temporary rental units regardless of rental duration. A new, expanded, changed or replaced use or structure can require a permit under section 7.3.
File with Code Enforcement using a scaled site plan, existing and proposed uses, setbacks, ownership or authorization, and wastewater information when required. The officer reviews completeness within 30 days and ordinarily decides a complete zoning application within 10 business days; a conditional-use referral follows the Planning Board process.
Sleeping space requires its own lawful approval.
For a conditional use, submit the application, plans and Town fee before review. The Town gives abutter and newspaper notice at least 10 days before the hearing, with newspaper expense charged to the applicant. The written decision is due within 30 days of the later hearing or requested information. Establish the approved use within 24 months and obtain approval before changing it. These procedures govern land-use approval.
Building permits apply to new construction, additions, relocation, replacement and structural alterations affecting safety. Repairs that do not affect structural safety are exempt from that construction-permit requirement. Under the Town Building Code section 5, repair or renovation within an existing footprint costs $1 per $1,000 of improvements, with a $25 minimum permit fee.
New construction costs $0.10 per square foot for unfinished areas and $0.20 per square foot for finished areas; unfinished basements in new construction are exempt from the fee. Manufactured or modular homes cost $0.20 per square foot, signage costs $5, and fences cost $1 per linear foot.
Give the Building Inspector at least 24 hours’ notice for required inspections. Regulated structures require a certificate of occupancy before occupation. Building Code violations may draw $100 to $2,500 for each offense, with each day of a proved violation a separate offense. These construction fees attach to regulated work on the property. Mount Desert Building Code sections 1–5 and 15 provide the work and fee rules.
Initiate a written appeal to the Zoning Board of Appeals within 30 days of notice of the final written decision. The ZBOA ordinance deems notice received three days after mailing to the applicant or filing in the Town Clerk’s office for other interested parties. Its section 4 requires a hearing within 30 days of receipt, subject to an agreed reasonable extension at the chair’s discretion, and newspaper notice at least 10 days before the hearing at the applicant’s expense.
The May 5, 2026 Land Use Zoning Ordinance section 7.7 authorizes de novo review of Code Enforcement permit decisions. The separately amended May 5, 2026 ZBOA ordinance section 4.D says an administrative-appeal hearing shall not be de novo. Those published provisions conflict on the review standard for Code Enforcement permit appeals.
LUZO section 5.8 separately specifies appellate review of Planning Board decisions. Enforcement decisions are excluded from these administrative appeals. The ZBOA ordinance section 4 sets the appeal procedure.